Phase 2 of the Precast Structure Taking Shape

Knoxville Collage 1Knoxville Collage 2Knoxville Collage 3

With the precast structure on the northern retail center/parking deck complete, crews move to the lower elevation of the southern retail center. Loading docks and ramps for the area appear with each new section erected.

On the northern end of the project, our last topping slab of the elevated deck has been completed and approved to start steel erection next week. Our next elevated pour will be in the loading dock area. Down below in the northern parking deck, our last “light duty” slab on grade concrete paving pour has been completed. Concrete test have confirmed strength that has allowed the beginning of our overhead rough-in of utilities.

Caisson work on the southern lower area of the project is now complete and concrete crews follow with the last few remaining pier caps. Both drill rigs have now move to the upper portion of the parking deck area. Overall, blue skies and no rain have been a blessing.

*The first image you see above is from our live web cam, which you can visit at here.