Precast Erection Complete

Knoxville CollageKnoxville Collage 2

The 250 ton capacity crane has been set to rest and the line of trucks hauling 60,000 pound concrete beams and double tees has ended. The precast erection of the southern retail center floor and parking deck is complete.

Concrete crews now begin their task of preparing the area for the leveling slab for the southern retail center. Loading dock ramp precast is also complete and we are preparing for the pour of the topping slabs and walls.

On the north end of the project, steel erection is complete for the main building with roofing operation soon to start. Entrance atrium steel erection is ongoing.