Permanent Power Energized at Northern Retail Center

UT Commons Collage 1Knoxville Collage 2

After the snow, ice and frigid weather of the past weeks, it has been nice to see days in the 50s and 60s with blue skies. This has allowed progress in the following areas:

Northern Retail Shops 

  • Permanent power activated
  • Paint of ceiling complete as well as walls in offices, pharmacy and guest service areas
  • Ceiling grid installed in all areas
  • Lighting and ductwork trim-out in ceiling grid
  • Bathrooms complete and ready for tile
  • Exterior EFIS near completion
  • Build-out of food service area released and ongoing
  • Piping of walk-in cooler and freezer complete
  • Remaining parapet and gutter installation ongoing
  • Atrium brick work ongoing
  • Atrium wall framing complete – MEP wall rough-in started
  • Atrium roofing to start early next week
  • Electrical trim out at painted walls 

Southern Retail Center

  • Atrium steel erection nears completion for this phase
  • 5 of the total 6 topping slabs have been completed – wet curing ongoing
  • Overhead MEP rough-in was ongoing before topping slab began
  • Under-slab electrical ongoing and coordinated with floor pours
  • In-slab plumbing ongoing and coordinated with floor pours
  • Block fill/painting of exterior block ongoing an point-up
  • Brick work near completion on main building – cleaning of brick ongoing
  • Transformer pads poured
  • Roof cap sheet system installed

 Shops A

  •  Structural steel erection ongoing 

Shops B

  • Underground MEP complete
  • Fine grading of sub-grade complete
  • Placement of stone complete
  • Installation of vapor intrusion system complete
  • Slab on grade forming ongoing

 Shops B-1 

  • Slab pour complete
  • Build-out framing ongoing
  • Overhead MEP and sprinkler piping ongoing
  • RTU Curbs and MEP roof penetration installed
  • Roofing to start next week

 Shops C

  • Underground MEP complete
  • Fine grading of sub-grade complete
  • Placement of stone complete
  • Installation of vapor intrusion system complete
  • Forming for slab-on-grade pour to start early next week

 Shops D

  • Building pad complete
  • Footing work to start on Monday